Amazon's public SLA for EC2 commits to 99.99% monthly uptime across a region. Fall a little below it and you are owed 10% of that month's bill. To collect, you open a case in the AWS Support Center and attach the logs. The request has to arrive by the end of the second billing cycle after the incident. Miss that date and the credit is gone.
We have no complaint about Amazon here. Its terms are public and anyone can read them. Plenty of negotiated service contracts work the same way, and those were written in private. We think a service credit you have to claim is one the supplier expects to keep.
Who has to notice the miss
A claim needs four things to go right. Someone on your side has to know the service level was missed. They have to know the contract pays for that. They have to know the deadline. Then they have to file.
The person who feels the outage is an operations lead. She wants the service back, and she has never read schedule C. The category manager who fought for the credit table in March has run three other renewals by the first bad month. Accounts payable sees an invoice for the usual amount and pays it.
The supplier knows all of it. Its monitoring recorded the miss to the minute, and its contract team wrote the claim window. It waits.
We call the result a paper remedy. It sits in the contract and never reaches an invoice.
Who keeps the clock
The supplier measures its own performance, and the definitions decide what counts. Scheduled maintenance is usually excluded. So is any failure the supplier traces back to your side.
The measuring period matters as much. A 30-day month has 720 hours. At a 99% monthly target, the service can be down for 7.2 of them and still pass. A four-hour outage on a Tuesday afternoon earns you nothing. At 99.9% the allowance drops to 43 minutes.
Work out what one hour down costs your operation before you accept a monthly average. Then read the dashboard at the next review with that number in mind. We have written about who owns that meeting, and the slide is usually green.
What the credit bought the supplier
Go back to the negotiation. You asked for 4% off. The supplier held its price and offered a credit table, with up to 10% of fees at risk every month. It sounded like accountability, and your side took it as a win.
So you paid for the credit. You gave up a price ask to get it, and every concession is a trade. A price cut would have shown up on every invoice with nobody lifting a finger.
Then read the sentence two lines under the table. Many credit schedules make the credits your sole and exclusive remedy for a missed service level. Amazon's SLA uses those words. With that sentence in place, the table caps what a failure can cost the supplier. A bad quarter costs it 10% of fees at most, and only if you ask.
The credit also comes off a future invoice. Amazon applies its credits against future payments and says they do not entitle you to a refund. You get paid for a failure only if you stay.
The supplier's lawyers wanted that table more than you did.
$48,000 at risk, $4,000 paid
Take an invented contract. A managed service costs $40,000 a month, or $480,000 a year, on a three-year term. Each month below the service level earns a credit of 5% of the monthly fee, so $2,000. Credits are capped at 10% a month, and claims are due within 30 days.
On paper the supplier has $48,000 a year at risk. Over the term that comes to $144,000.
Now run the term. The service level is missed in seven of 36 months, so $14,000 is owed. Your team files twice, both times after an outage loud enough to reach a vice president. The supplier pays $4,000. The other $10,000 expires, one 30-day window at a time.
A credit that waits for a claim measures your paperwork. The supplier measured its own performance months ago.
So $144,000 of paper risk produced $4,000 of cash, under 3% of it. We care less about the lost $10,000 than about what it tells the supplier. Five misses went by without a word from you. An account manager walking into the renewal knows nobody reads the service schedule.
Three changes to ask for
Ask for the credit to be automatic. The supplier measures the service level already, so it can take the credit off the next invoice without a claim. If it refuses, you have learned how much of that table it expected to pay.
Ask for a monthly service report with the invoice, and have accounts payable hold any invoice that arrives without one. We would sooner argue about one number every month than discover seven of them at renewal.
Then narrow the sole remedy sentence. Credits can stay the remedy for an ordinary miss. Three missed months in any six should give you the right to leave without a fee. Suppliers resist this change hardest, and we read that as a sign of where the value sat.
If you can only get one, take the automatic credit.
Bring the missed months to the renewal
We built Outcomes & Learning around one test. A saving counts when it shows up in what you paid. Forty-five days after a deal closes, Whispor reads the invoices against a baseline you agreed before work began. We hold a service credit to the same test ourselves. Agreed and unpaid, it is still pending.
Whispor also remembers what each supplier conceded and committed to, and that record feeds the next brief. A credit table is a commitment. We would want the seven missed months sitting beside it when the renewal brief gets written. We think a remedy nobody collects is a price cut you traded away for nothing.